Project Scope: As part of modification works to the existing water reticulation system, this project involved design and build modifications to the existing Tamatea Reservoir.

Physical works involved in the contract included:

  • A Structural assessment of the reservoir – post tensioned walls, pilaster panels, floor slabs, ring beams etc.
  • Structural modifications to the reservoir for new inlet and outlet pipe penetrations including structural supports for the pipe work
  • Design and installation of a baffle curtain within the tank
  • Construction of a new valve chamber outside the reservoir
  • Remedial repairs to the tank structure
  • Cleaning and disinfection of the reservoir

Click here to return to the previous page.

Make an enquiry

If there is a particular project you have in mind, or if you wish to ask us a general question then, click here.

Spartan Construction overview

Our overview proviced a more in depth view of Spartan Construction as a leader in construction.

Health & Safety

Spartan Construction has a culture that considers Health & Safety, Quality, and Environmental issues a high priority.

Safety Policy
Quality Policy
Environmental Policy