Te Uku Windfarm

  • Client
  • Consultant
  • Value
  • Meridian Energy Limited
  • Bloxham Burnett & Oliver
  • $29.5 million


Project Scope: The Te Uku windfarm project consisted of the construction of the civil infrastructure for a 64MW wind power site including the road network and turbine foundations.

Major works involved in the construction contract included:

  • 26km of road network, purpose built for access and the delivery of heavy and long load wind turbine components.
  • Extensive erosion and sediment control design, construction, monitoring and decommissioning of up to 170 control devices.
  • Establishment of an on-site concrete batching plant
  • Construction of 28no turbine foundations consisting of 1335 tonnes of reinforcing steel and 12,000m3 of concrete.
  • Positioning of electrical conduits and free issue holding down bolts and casting onto foundations.
  • Installation of 70km of high voltage electrical cables between turbine sites and the substation
  • Construction of substation platform and building foundations
  • Construction and positioning of 28no transformers and 6no circuit breaker foundations.

Click here to return to the previous page.

Make an enquiry

If there is a particular project you have in mind, or if you wish to ask us a general question then, click here.

Spartan Construction overview

Our overview proviced a more in depth view of Spartan Construction as a leader in construction.

Health & Safety

Spartan Construction has a culture that considers Health & Safety, Quality, and Environmental issues a high priority.

Safety Policy
Quality Policy
Environmental Policy