Waikeria Potable Water Project
Department of Corrections
CLIENT:
2021 - 2022
YEAR:
This project was for the construction of a Greenfields water treatment plant for the Department of Corrections.
Major works included:
Roading and platform earthworks (10,000m3)
Roading and platform surfacing, 3500m2 in total
A new production bore pump and headworks
Design and build of a 1.5 ML water storage reservoir
4000m of underground potable water reticulation
Piping and pump supply from reservoir to farm supply reticulation
Wastewater pipe from the water treatment plant to a connection point near the Waikeria Prison Development
Supply and install of Greensand filter system
Mechanical installation, including above ground stainless steel pipework, equipment, valving and instrumentation.
Containerised water treatment plant, complete with backwash system, UV, chlorine, and caustic treatment, including electrical controls and telemetry
Concrete foundation structures, valve chambers and timber canopy construction
Planting of visual mitigation and security fencing
Testing, commissioning and proving