CLIENT:
YEAR:
Major works included:
Design of temporary works and the installation of a clay cofferdam and dewatering to bund off and control the canal.
Demolition of the existing pump station componentry to allow for new concrete and metal work.
Excavation and subgrade improvements including 14m timber piles with concrete pile cap foundations.
The new pump station inlet comprised of precast concrete walls placed on the concrete pile cap foundations. The panels were tied in with a concrete floor and in-situ stitch joints to the existing structure.
The design and construct for a precast hollowcore deck which included an in-situ concrete topping slab. These items required a PS1 and PS3.
The removal and replacement of all mechanical componentry with the replacement of large sluice gates.
Site reinstatement which included retaining walls, timber steps and fences, metal access tracks and grassing.
This project was completed in May 2018.