King Country Energy
CLIENT:
2014
YEAR:
The civil scope of the works for this project included:
Removal of two existing obsolete turbines and associated draft turbines etc
Building strengthening including pile installation of new turbine reinforced concrete foundation works
Turbine foundation work . This work requires sequencing to ensure equipment installation occurs in the right order.
Placement of draft tube a12030, turbine a11088, MIV (main inlet valve) a12008 and generator 1-3206-531.
Lowering of the tailrace by 0.5m, demolition, excavation and construction of new reinforced concret tailrace
New penstock foundation block and plinths; and installation of the new penstock
Installation of bored reinforced concrete piles